In November  2014, Cajun was  awarded  a  contract  to  install  
 pre-cast concrete piling for the heater foundations of the  
 Ethane Cracker Unit at the Sasol Mega-project in Westlake,  
 La. The project was owned by Sasol Chemicals, USA, with design  
 and management services by Fluor Technip Integrated (FTI). This  
 startup involved two driving cranes, along with one receiving and  
 handling crane to support them. The piling installed for this unit  
 were 1,648 each 18-inch by 66-foot PCCP and 194 each 14-inch by  
 66-foot PCCP, with the piling material being furnished by the client. 
  Cajun worked closely with the client to manage both the pile  
 delivery and installation schedule. Due to soil conditions and pile  
 spacing, quite a bit of upheave was noticed in the installed piling.  
 After working with the engineers, Cajun coordinated cutting of the  
 piling to the correct design elevation prior to installation of the  
 concrete foundation. 
 While performing this work, Cajun was approached by FTI to  
 assist with the redesign of a storm water retention pond, referred  
 to as Pond #6. The original design was for a structural concrete  
 lined pit. Due to the proximity of existing underground pipelines,  
 as well as overhead power lines, open cut excavation for this  
 installation was not an option. Cajun proceeded to design and  
 install a braced sheet pile sump consisting of PZC26 sheet piling  
 with walers and struts in lieu of a cast-in-place concrete structure.  
 This resulted in not only a cost savings for Sasol, but also aided in  
 constructability. 
 As work progressed, Cajun was awarded with pile installation  
 in other units of the facility, including the LDPE, LLDPE, EO/EG  
 and the interconnecting pipe rack foundations. This resulted in a  
 total installation of 13,396 PCCP, ranging in size from 14 inches by  
 40 feet to 18 inches by 66 feet. In addition to the PCCP, there were  
 also numerous ACIP piling (5,931 total), drilled shafts (291 total)  
 Photos courtesy of Cajun Industries 
 Sasol  
 Mega-project  
 Pile Installation 
 Cajun installed thousands of different  
 pile types and increased its contract  
 value by more than 700 percent on  
 this mega job 
 Submitted by Cajun Industries 
 This resulted in an increase of  
 more than 700 percent of the  
 original contract value for Cajun. 
 92  |  EDITION 6 2019  www.piledrivers.org 
 
				
/www.piledrivers.org