PROJECT SPOTLIGHT 
 Many constraints  
 and many pile  
 types for Boh Bros.  
 Construction Co., LLC 
 Submitted by Boh Bros. Construction Co., LLC 
 The World Trade Center at the intersection of Canal  
 Street and the Mississippi River in New Orleans  
 is being converted into a Four Seasons Hotel and  
 Residences. Interior renovations plus additions to three sides of  
 the building are being completed by a joint venture of AECOM  
 Tishman and Woodward Design + Build of New Orleans. The structural  
 design was led by Nick Mannix, P.E., manager of Woodward  
 Engineering Group. 
 Soil conditions were more variable than desired, but “welcome  
 to New Orleans.” Very soft clay for the first 30 feet was followed by  
 sands and silt at 45 feet (some borings had medium-dense sand).  
 The stiff clay layers changed to dense sand at 90 feet. A test pile program  
 was conducted on 14-inch open-end pipe piles. PDAs tested  
 every probe pile at end of initial drive and at various intervals of up  
 to seven days. Then static load tests, two in compression and two  
 in tension, followed. 
 The main addition foundations required over 200 each 14-inch  
 by 0.250 wall by 110-foot open-end pipe piles. These were driven in  
 two pieces with a full-penetration weld. Many of these piles were  
 extremely close to the existing building, which required strategic  
 planning in order to allow equipment access. After driving, all pipe  
 piles were filled with sand and topped with concrete to cutoff elevation. 
  The piles were driven to grade; therefore, open holes posed  
 a significant hazard to personnel walking through the site. To remedy  
 the hazard, Boh’s carpentry shop-built hundreds of wooden  
 pile covers to go over both newly driven piles and to replace countless  
 covers, which were constantly being damaged by construction  
 traffic moving through the site. 
 The most difficult portion of the addition was the riverside. It  
 was hemmed in between the existing building and the Mississippi  
 River floodwall with an active railroad track that ran through this  
 section. Many of the piles in this area were also under an overhang  
 that could not be removed. The 20-plus highly loaded piles were  
 14-inch  by  110  feet,  driven  in  13.75-foot. There were  also  twenty  
 10.75-inch by 55-foot pipe piles driven in 13.75-foot pieces. The  
 pipe in pieces were driven by an extended reach forklift. Extra  
 excitement was caused by the requirement to install sheet piles  
 under low headroom to provide support for five separate excavations  
 next to the railroad track. The wales and struts were fabricated  
 off-site at the Boh Bros. yard and set into the cofferdams after  
 Photos courtesy of Boh Bros. 
 www.piledrivers.org  PILEDRIVER  |  103 
 
				
/www.piledrivers.org