the required sheet piles and pipe piles had been installed. Precise  
 field measurements were required to ensure that the wales and  
 struts fit within the sheet piles and missed the contained pipe piles. 
 Underground obstructions, both known and unknown, posed  
 challenges daily. A duct bank, which provides power to the adjacent  
 Harrah’s Casino and  Audubon Aquarium, was  identified  
 before the project started and ran through the middle of the site.  
 The vital and dangerous duct bank was excavated and exposed at  
 several locations to identify its exact location and avoid conflict.  
 Several unknown utilities were also encountered and subsequently  
 identified without incident. Other frequent obstructions included  
 old pile caps, timbers and miscellaneous debris. In addition to the  
 underground obstructions, as many as four trains would pass within  
 a few feet of driven pile and sheeting locations on any given day.  
 With no daily train schedule available, Boh Bros. would have limited  
 advanced warning to move equipment safely out of the path of  
 the trains. Frequent conflicts with underground obstructions and  
 train schedules required Woodward and Boh Bros. to continuously  
 work together to expedite solutions. 
 The addition on the north side of the building increased the pile  
 variety by requiring Boh Bros. to drive over 70 each treated timber  
 piles ranging in length from 65 to 70 feet as well as additional long  
 PROJECT SPOTLIGHT 
 At one point, Boh had one crawler crane  
 rig, two low overhead rigs, one sheeting  
 rig and one pile fill crew all working at the  
 same time 