mobilize during  the  timeframe  requested by  IHI. Once  the  sheet  
 pile material was delivered to the site, Cajun’s crew began immediately  
 vibrating the sheet piles into place at the Z-4001, Z-4002 and  
 Z-4003 basins. 
 It was at Basin 4003 when Cajun’s sheet pile crew came across  
 its first challenge. After Cajun was awarded the basin scope of work  
 and before mobilizing the site to install sheet piles, Georgia Power  
 installed an electrical transmission line tower in the footprint of  
 the  Z-4003 First Flush Sump. This  required Cajun  to  re-engineer  
 the 4003 TRS system around the newly installed tower. The Cajun  
 team had to strategize the process of shoring and installing sheet  
 piles around a tower pole and under power lines, which had zero  
 tolerance of being disturbed. To help solve the installation challenge, 
  Cajun utilized a Giken Silent Piler to install the sheet piles  
 under the power line, due to the equipment’s design capabilities.  
 The advantage of the Giken Silent Piler design is that it sits on top  
 of the sheet pile wall and pushes the sheet piles without vibration  
 or excessive noise. The use of the system eliminated the  
 overhead  obstruction  challenges and  potential  damage  to  the  
 previously installed tower pole. The Giken rig installed 200 linear  
 feet of  sheets in one week. After completion of the TRS systems  
 at each respective basin, the heavy civil operations of the basin  
 scope commenced. 
 While the civil basin work was taking place, Cajun was awarded  
 additional scope to perform an exploratory test pile program for  
 helical piles on the  site. If successful, Cajun would  install helical  
 piles in  areas  where  new  pipe racks were required adjacent to  
 existing pipe racks inside the existing facility. After installation  
 and successful testing of the helical piles, Cajun issued the report  
 to IHI Engineering. The helical piles met the intended loads but  
 were not approved for use by the Owner. IHI informed Cajun that  
 Kinder Morgan would not allow helical piles to be installed on the  
 site due to the re-approval process timeframe by the engineer of  
 record to create the substitution. Therefore, designed H-piles were  
 required to be installed at all locations. After analyzing the work  
 areas and the overhead clearances at the existing pipe racks, Cajun  
 decided that a seven-foot H-pile was the longest section of pile that  
 could be installed under the existing clearances. Each pile was 77  
 feet in length, requiring Cajun to install 11 pile sections at each  
 pile location. With 13 piles required, a total of 130 full penetration  
 structural welds were required to combine pile sections during the  
 installation process. The installation duration of the H-piles was  
 contingent upon how fast the welders could fit up and weld two  
 sections of H-piles. This scope required a specialized warehouse  
 style forklift, box leads and a hydraulic impact hammer to install  
 the H-piles. The forklift would give Cajun the ability to fit into challenging  
 areas in the plant, where vertical headroom was an issue.  
 Cajun began H-pile installation on Nov. 30, 2017 and completed the  
 scope on Jan. 22, 2018. 
 Cajun completed the entire scope of work in March 2018, after  
 being on site for an entire year. Cajun mobilized the project to initially  
 install 945 piles for a six-month duration. Because of Cajun’s  
 dedication to safety, quality and production on site, an additional  
 $13,000,000  in  scope was  awarded  to Cajun, which  increased  its  
 on-site duration from six months to one year. Cajun added value  
 to the project with its integrated project team approach, not only  
 with its other business groups and sister company, but also with  
 the client, owner and engineers. Even with all of the unanticipated  
 extra work and unforeseen delays, challenging working conditions  
 and congested work areas, Cajun completed the project with zero  
 injuries and within  a timeframe  that was  acceptable  to IHI and  
 Kinder Morgan.  t 
 PROJECT SPOTLIGHT 
 Bathub and sheet piles at the 4001 basin 
 110  |  EDITION 6 2019  www.piledrivers.org 
 
				
/www.piledrivers.org