HARTMAN  
 ENGINEERING 1.716.759.2800  |  www.hartmanengineering.com 
 4910 Ransom Road, Clarence, NY  14031-2141 
 Our firm has many years experience taking on the challenges of difficult design problems in the  
 specialized area of cofferdams, retaining walls, foundation support, and damaged structures 
 Project management 
 Due to the sheet pile coating delivery and  
 durations, APC had to begin driving concrete  
 piles first and then sheet and mooring  
 pile installation concurrently. Previous  
 projects at this location were constructed  
 by driving sheet piles first and concrete  
 piles second. This afforded those previous  
 projects the ability to use the sheet piles as  
 a seepage cutoff wall and allowed for excavation  
 to occur after the sheet piles were  
 installed. The traditional method allows  
 excavation to be completed after sheet pile  
 installation, which minimizes water intrusion  
 on the jobsite. Further, the traditional  
 method allows the crane to be sitting at a  
 higher elevation. 
 In order to meet the aggressive schedule  
 and sheet pile delivery time constraints,  
 APC’s  approach  required  excavation  to  
 begin prior to and during pile installation.  
 Excavated materials were used to build  
 an earthen dam to keep the excavation  
 from flooding. This approach allowed us  
 to  begin  concrete pile installation  safely  
 while sheet piles were being coated. Once  
 we received sheet piles, APC began installing  
 sheet  piles  and  mooring  pile  from  
 inside the  excavation  with  our  compact  
 and lighter crane concurrently along with  
 the concrete pile installation. 
 The  challenge  to  this  approach  was  
 the fact that the traditional method of  
 driving sheets first was not an option due  
 to the lead time on the sheet coatings  
 which would have had a negative cost and  
 schedule impact to the project. Further,  
 this approach required a larger excavation  
 next to an existing slip with cranes  
 and equipment working in a 70-foot-wide  
 excavation  verses  a  much  smaller  and  
 more manageable excavation that would  
 have been protected from the water by  
 the  sheet  bulkhead  wall  installation  as  
 other, previous projects in this location  
 were constructed. 
 With a team approach with the general  
 contractor, APC effectively shortened  
 the overall project schedule through an  
 innovative  approach  for  the  Northern  
 Expansion  Phase  II,  Slip  C,  Phase  III  
 Bulkhead  Project.  Although  APC’s  nontraditional  
 approach used on this project  
 presented significant pile installation  
 challenges,  the  APC  team  successfully  
 overcame the project schedule restraints  
 and jobsite conditions to deliver a quality  
 product to the client while maintaining a  
 zero-incident project.  t 
 PROJECT SPOTLIGHT 
 90  |  EDITION 6 2019  www.piledrivers.org 
 
				
/www.hartmanengineering.com
		/www.piledrivers.org