scattered out all over the project site and had to be moved on multiple  
 occasions to accommodate other contractor work scopes. As  
 space near  Cajun’s work areas became available, materials were  
 moved again to make installation into the basin safer and easier.  
 The consistent re-staging of heavy and large materials was a constant  
 obstacle that Cajun had to overcome as construction activities  
 progressed. 
 Scope of work 
 At the time of Cajun’s mobilization to the island, the project had  
 already  commenced,  and other  contractors were on  site. Cajun’s  
 piling crew was brought to the site because of Cajun’s reputation  
 on its three core principles: safety, quality and production.  
 Cajun’s history of providing the highest level of quality was a  
 major factor in being awarded the initial scope of the piles at the  
 MMLS structures. 
 Having another piling contractor on site presented a challenge  
 that was not normally present on other piling projects. Cajun  
 crews were informed to respect the work of the other piling contractor  
 and to assist them in any facet necessary in order to benefit  
 all parties involved in the project. 
 Cajun’s scope of work was designated to the elevated portions  
 of the island and the west side MMLS structures, eliminating  
 any scheduling or construction conflicts with the other piling  
 contractor. With the MMLS pile location tolerance being a high  
 priority, Cajun mobilized specialized pile installation equipment to  
 ensure that all piles installed could meet the required plus/minus  
 two-inch pile location tolerance as stated by the project specifications. 
  The specialized system consisted of a 275-ton Terex crane,  
 Berminghammer hydraulic lead system with driving template  
 and a diesel impact hammer. The Berminghammer hydraulic lead  
 system gave Cajun the ability to raise/lower the leads on a vertical  
 travel system to ensure the top of pile location accuracy, regardless  
 of the elevation of the crane tracks. The hydraulic horizontal  
 offset of the leads enabled the piles to be pivoted up to 30 degrees  
 in both directions to ensure that the piles could be driven square  
 to axis, as drawn on the project plans. The leads also married up to  
 a template system, which was laid out on the working surface by  
 Cajun surveying, to ensure that the piles were placed in the exact  
 designed locations. 
 Expanding project scope 
 After being on site for two months and installing 15 percent of the  
 original contract pile quantity, Cajun was presented an opportunity  
 to provide IHI with turnkey pricing on four large basins (Z-4001  
 Refrigerant Impoundment Basin, Z-4002 MR/LNG Impoundment  
 Basin,  Z-4003  First  Slush  Sump  and  Z-4010  Observation  Basin)  
 that were required for the project. During the estimating phase of  
 PROJECT SPOTLIGHT 
 Limited access sheet piles at the 4003 basin Installing the limited access H-piles at the 791 area 
 108  |  EDITION 6 2019  www.piledrivers.org 
 
				
/www.piledrivers.org