allowed Chesterfield’s crews to work two shifts for most of the  
 project, aiding in keeping as close as possible to a very tight  
 construction schedule. 
 Additional challenges resulted from needing to construct both  
 sides of the pier sequentially due  to the fact that one side of the  
 pier held up the opposing side with hot-dipped galvanized double  
 channel wales and 2.5-inch high-strength threaded bars. The  
 installation of the structural exterior wales and tie rods had to be  
 coordinated around mid-tide and lower tide conditions due to Port  
 Jef ferson tides that run six to seven feet in range. During some of  
 the storms encountered during the construction period, the entire  
 pier was submerged, putting a temporary halt to construction. The  
 project crew experienced four “nor’easters” in the month of March  
 2018 alone, and the winter of 2017-2018 was a very snowy season,  
 as well. The existing pier structure(s) were up to 100 years old or  
 more. We encountered varied existing construction, including  
 steel, timber sheet piling and timber cribbing. 
 Unfortunately, some of this old construction conflicted with the  
 new construction, which occasionally necessitated dive crews to  
 help move obstructions from the line of the new SSP bulkheading.  
 PROJECT SPOTLIGHT 
 Early stages beginning at the north end of the pier 
 88-foot and 90-foot SSP stagger stacked, ready for installation 
 Steel cap installation on west flanking bulkhead at landward end of pier 
 Bulkhead progressing in same location as previous bulkhead along the  
 west side of the pier 
 Fifty-foot SSP being hoisted into place for the east flanking bulkhead 
 98  |  EDITION 6 2019  www.piledrivers.org 
 
				
/www.piledrivers.org